Final Paving of Eaton Road to Begin Week of May 4 th

The Town of Swanzey has engaged B.U.R. Construction of Newport to reconstruct Eaton Road from Sawyers Crossing Road to Greenleaf Road. This project has included reclaiming the asphalt, improving drainage and ditch lines, replacing cross culverts, improving the road base, and then ultimately repaving the road. Most work and initial paving was completed in 2019.

Final clean up after the winter along with loaming and seeding for the majority of the project has been completed this spring. Remaining work includes the following:

May 4 – 8: Pavement repairs, final paving of the road and driveway aprons.

May 11 – 15: Shoulder / driveway graveling, line painting, and general final clean up.
Motorist can expect one lane traffic and minor delays during working hours.

The reconstruction of Eaton Road is the first project to be funded by a $3 million bond for road reconstruction projects approved by voters at the 2019 Town Meeting.